Ghana Parliament Reviews Boankra Integrated Logistics Terminal Project

Story Highlights
  • BILT project to investigate a $3 billion lawsuit threat
  • The lawsuit threat is from APSL
  • Justmoh Construction Ltd's contract is being regularized

Ghana’s Parliamentary Select Committee on Roads and Transport visited the Boankra Integrated Logistics Terminal (BILT) project to investigate a $3 billion lawsuit threat from Ashanti Port Services Limited (APSL).

Contract Termination by Mutual Agreement

The Ministry of Transport (MoT) stated the contract with APSL was terminated by mutual agreement due to their inability to secure funding despite extensions. The project is now funded by the Ghanaian government.

APSL’s Lawsuit Threat

APSL claims the Ghana Shippers’ Authority (GSA) wrongfully terminated the contract and is seeking $3 billion in damages. The MoT denies receiving any official lawsuit.

Project Status and Completion

The committee toured the site and reported 40% completion of phase 1, including civil works and infrastructure. The project is expected to be finished by 2026.

Committee’s Recommendations

  • The committee commended the progress and quality of work.
  • They urged securing funds to ensure timely completion.
  • Increased community engagement and employment were suggested.
  • Justmoh Construction Ltd’s contract is being regularized.

Justmoh Construction Ltd’s Commitment

The new contractor, Justmoh Construction Ltd, pledged to complete the project on schedule and highlighted its significance for Ghana. They requested expedited release of funds to move forward.